The page lists 14 deliverables related to the research project "MinWaterCSP".
title and desprition | type | last update |
---|---|---|
Delivery test facilityDelivery of manufactured components to test site, installation and commission of test facility. This will involve the successful construction of the full scale hybrid cooling unit. The installation of all measuring and data logging equipment will also be completed together with a strategy for data capturing and analysis. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Demonstrators, pilots, prototypes | 2019-10-04 |
Full-scale CSP cooling fanFull-scale CSP cooling fan manufactured and installed for testing. The full-scale CSP cooling fan will be installed in the full-scale test facility near SUN together with all measurement apparatus and data logging equipment. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Demonstrators, pilots, prototypes | 2019-10-04 |
3D modelling hybrid cooling system3D modelling of the hybrid cooling system for demonstration / marketing purposes as well constructability reviews and results. The model will be created in a typical commercial software CAD package and stored in electronic files. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Websites, patent fillings, videos etc. | 2019-10-04 |
Scale model of CSP cooling system fanScale model of CSP cooling system fan manufactured and installed in wind-tunnel for testing. The deliverable will be a manufactured, scaled model. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Demonstrators, pilots, prototypes | 2019-10-04 |
Communication / Dissemination actions at events – part 2One report covering event participation and contributions (external and own events) – update for period since D10.4. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Documents, reports | 2019-10-04 |
Dissemination actions: print/digital tools – part 3One report covering press-releases, articles, eNewsletters and social media activity – update for period since D10.6. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Documents, reports | 2019-10-04 |
Dissemination actions: Print/digital tools – part 2One report covering press-releases, articles, eNewsletters and social media activity – update for period since D10.3. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Documents, reports | 2019-10-04 |
Communication / Dissemination actions at events – part 3One report covering event participation and contributions (external and own events) update for period since D10.7. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Documents, reports | 2019-10-04 |
Communication and dissemination materials – part 1One report covering project website, communication and dissemination materials. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Documents, reports | 2019-10-04 |
Deluge test bundle constructedDeluge test bundle constructed and commissioned at the relevant industrial site. This would involve the successful installation of the test bundle at the test site in Morocco, complete with all the measuring and data logging equipment. A visual inspection and data analysis strategy will also be in place. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Demonstrators, pilots, prototypes | 2019-10-04 |
Dissemination actions: Print/digital tools – part 1One report covering press-releases, articles, eNewsletters and social media activity. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Documents, reports | 2019-10-04 |
Communication and dissemination materials – part 2One report covering project website, communication and dissemination materials – update for period since D10.2. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Documents, reports | 2019-10-04 |
Communication / Dissemination actions at events – part 1One report covering event participation and contributions (external and own events) for the past / future period. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Documents, reports | 2019-10-04 |
30ft reference fan complete30 ft reference fan manufactured and installed for testing. This fan will be delivered and installed in the existing air-cooled condenser of Matimba power station, RSA. Programme: H2020-EU.3.3.2.4.;H2020-EU.3.3.2.2.;H2020-EU.3.3.2.1. - Topic(s): LCE-02-2015 |
Demonstrators, pilots, prototypes | 2019-10-04 |